Amendment of the announced by CFHC on behalf of CTBC Bank the construction cost of Xinyi headquarters bldg. reaches an accumulative total of over 500 million.
1.Date of occurrence of the event:2023/11/24
2.Date of the original announcement and reporting:2018/07/27
3.Summary of the content originally announced and reported:Based on the Joint
Construction contract:The occupancy permit shall be obtained within 55
months of the construction license being obtained.
4.Reason for change and its main content:Amendment of the Joint Construction
contract: The occupancy permit shall be obtained within 69 months of the
construction license being obtained. Other content remain unchanged.
5.Effect on the Company's finance and business after the change:none
6.Any other matters that need to be specified:none